Factory and production line relocation: a planning guide
Relocating a factory or a production line is more than loading machines onto a truck. A successful move rests on decisions taken in advance: a review of the current and target layout, a planned dismantling, moving and installation sequence, infrastructure that is ready, and pre-start-up tests defined before the first machine is disconnected.

Before the move: inventory and layout
Start with a list of every machine: brand, model, serial number, current fault codes and photos. Then compare the current layout with the target layout side by side: in what order will the machines stand in the new building, how will the material flow change, and is there enough room left for maintenance and safety access?
Power, compressed air, water and data connection points in the target area, and whether the floor suits the machine weights and the anchoring method, should be clear before anything moves. If the infrastructure is not ready, a machine that has reached its new place still cannot run.
It also helps to record the machines while they are still running: current fault codes, recent maintenance records and short videos of operation make it easier to tell whether a problem at the new site comes from the move or from a condition that already existed.
Plan the dismantling, moving and installation sequence
The production schedule decides which machine stops first and which is moved last. When a line consists of several machines, the installation order in the new layout sets the sequence: the equipment installed first should be moved first.
Marking cables, hoses and connection points, numbering parts and photographing each step during dismantling speeds up reinstallation and reduces the risk of errors. Sensitive parts are packed accordingly.
If a production stop cannot be avoided, building up stock before the move or relocating lines in phases can be considered. Which approach fits depends on the plant's order plan and the dependencies between lines.
Lifting, rigging and transport
Lifting and moving heavy machines is an engineering task of its own: lifting points, equipment selection, route, and door and road dimensions are checked in advance. Whether a machine is repositioned within the plant or moved between plants or countries, the question is the same: by which method, in which order and with which safety measures?
Project-specific risk assessments, method statements and work permits are prepared for lifting and moving operations, and the work is carried out in line with the plant's own health and safety system.
In international moves, packing, transport engineering and repositioning at the destination are tied to the same plan; which parts of a machine travel separately is decided during dismantling.
Installation, alignment and connections at the new site
Once the machine is in place, it is positioned, levelled and aligned. At line and conveyor transfers, the alignment between machines directly affects product flow; laser tracker measurement checks position and dimensions at this stage, and an as-built survey helps document the new layout.
Mechanical assembly, power and control connections are then completed in a coordinated way.
Tests and production start-up
Pre-start-up tests should be defined before the move: which function tests will be run, and which result counts as “ready”? When acceptance criteria are written down from the start, commissioning is based on measurement rather than debate.
Operator briefings and, where needed, technical training help reduce stoppages in the first days in the new layout. Scheduling the first preventive maintenance for relocated robots and machines is also a good start.
In the first production days, product quality and cycle times can be compared with the values recorded before the move, so that the cause of any difference is found early.
The move at a glance
- Survey and planning: Current and target layout review, work schedule. What to prepare: Equipment list, layout drawings, production schedule.
- Dismantling and packing: Marking connections, numbering, packing. What to prepare: Photos, connection list.
- Lifting and transport: Rigging, route, transport plan. What to prepare: Risk assessment, method statement, work permits.
- Installation and alignment: Positioning, levelling, connections. What to prepare: Ready infrastructure, measurement plan.
- Testing and commissioning: Function tests, operator briefing. What to prepare: Acceptance criteria.
One point of contact for coordination
In a relocation project, the dismantling crew, the haulier, the electrical and mechanical teams and the production team all depend on the same schedule. STU Servis can take on the planning, scheduling and coordination of factory and line relocation projects as a single point of contact, handling supplier and subcontractor coordination, progress tracking and risk management together with project documentation.
Relocation should not be treated separately from maintenance, remote analysis and spare parts. STU Servis handles these services within one connected service structure, so periodic maintenance and spare-parts support can continue with the same contact once the machine is running at its new site.
Related services:
- Factory and production line relocation
- Machinery moving & heavy haulage
- Installation and commissioning
- Industrial metrology & site layout
- Project management
- Health & safety
Frequently asked questions
How long does a factory relocation take?
It depends on the number of machines, the dismantling and installation sequence, how ready the infrastructure in the target area is and the scope of testing. Instead of a generic duration, a project-specific work schedule is prepared after the current and target layouts have been reviewed.
Does production have to stop completely during the move?
Not always. Lines can be moved in phases, or stock can be built up before the move; which option fits is decided by the order plan and the dependencies between lines.
What information is needed for a quote?
Equipment brand, model, serial number, current fault codes, production schedule, current and target layout drawings and any photos. Response time and commercial terms are confirmed per request.
Do you also move machines abroad?
Our machinery moving service covers repositioning within the plant as well as international machine moving and transport engineering. Dismantling, packing and repositioning at the destination are part of the same plan.
How is a relocated machine commissioned at the new site?
It is positioned, levelled and aligned, assembly and control connections are completed, and production starts after the function tests and acceptance criteria defined in advance; operators are briefed on the new layout.